S.No.StateDivisionRangeWork NameWork Duration(In Years)Scheme HeadEstimate YearOperation YearRef. No.Funds Allocated(In Rs.)Expenditure(In Rs.)View EstimateView Monthly ExpenditureSite Scanned Map
1 RajasthanDCF Chhatargarh RANGE SATTASARCsp Dkd 25-50 Rd Ls-'Csp Dkd 25-50 Rd Ls'8OTHER2019Fourth Year Operation22187440.000.00
2 RajasthanDCF Chhatargarh RANGE SATTASARDfl 12 Dkd (Advance)-'Dfl 12 Dkd'5OTHER2019Pre-Plantation Operations591270467.000.00
3 RajasthanDCF Chhatargarh RANGE SATTASARBp 8 Dkd-'Bp 8 Dkd'8OTHER2019Pre-Plantation Operations21406776.000.00
4 RajasthanDCF Chhatargarh RANGE DANTORSds 1 Swm-'Sds 1 Swm'7OTHER2023First Year Operation361055525.000.00
5 RajasthanDCF Chhatargarh RANGE DANTORSds 15 Kjd Campa-'Sds 15 Kjd Campa'7OTHER2022Pre-Plantation Operations361055525.000.00
6 RajasthanDCF Chhatargarh RANGE DANTORSds 16 Dwd-'Sds 16 Dwd'7OTHER2022Pre-Plantation Operations36844420.000.00
7 RajasthanDCF Chhatargarh RANGE DANTORSds 17 Pb-'Sds 17 Pb'7OTHER2023First Year Operation36844420.000.00
8 RajasthanDCF Chhatargarh RANGE CHHATARGARH 132 Kv Dc Lunkaransar To Chhatargarh Transmission Line-'132 Kv Dc Lunkaransar To Chhatargarh Transmission Line'10OTHER2023Third Year Operation23407503.000.00
9 RajasthanDCF Chhatargarh RANGE CHHATARGARH 220 Kv Dc Gajner To Chhatargarh Transmission Line-'220 Kv Dc Gajner To Chhatargarh Transmission Line'10OTHER2023Third Year Operation14658616.000.00
10 RajasthanDCF Chhatargarh RANGE CHHATARGARH 6 Gm-'Dfl 6 Gm'7OTHER2023Third Year Operation10109555.000.00
12345678910...